FIFTY8ONV's site is very close to being sealed, as all of the doors and windows will be installed by the end of the month. The internal brickwork is complete and the communal, rooftop pool has been cast. The team is working on the drop ceiling structures and built-in TV units on the first and second floors. The tiling has begun in the kitchens and bathrooms as well. Externally, plastering and the initial phases of the paint finish have commenced.